[GRA3][Infrastructure] - Background electrical work - room TGBT15
Scheduled Maintenance Report for Network & Infrastructure
Completed
Start time : 13/03/2023 07:00 UTC
End time : 13/03/2023 15:00 UTC
Service impact : None
Service improvement : Following our continuous improvement policy, we are doing some electrical background work for the room TGBT15
Posted Mar 13, 2023 - 15:33 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 13, 2023 - 07:00 UTC
Scheduled
Start time : 13/03/2023 07:00 UTC
End time : 13/03/2023 15:00 UTC
Service impact : None
Service improvement : Following our continuous improvement policy, we are doing some electrical background work for the room TGBT15
Posted Mar 11, 2023 - 05:58 UTC
This scheduled maintenance affected: Infrastructure || GRA (GRA3).