We will move routers ldn-1-6 and ldn-5-6k on Telehouse London to a new space in the new building West. We will also switch the 10G links between London and Roubaix on new equipment in 100G Infinera (chassis DTN-X).
The work will take place the night separating 30 to 31/01 starting from 00:00 CEST, 11pm local time.
Update(s):
Date: 2013-01-31 04:52:42 UTC Both routers were permanently moved to the rack.
Date: 2013-01-31 04:52:16 UTC The router ldn-5-6k is on and pings.
Date: 2013-01-31 04:51:49 UTC the router ldn-5-6k is off.
We are moving the chassis.
Date: 2013-01-31 04:51:06 UTC Router isolated.
We will begin disconnecting the fibers.
Date: 2013-01-31 04:50:43 UTC All links are reconnected to ldn-1-6k.
We are isolating ldn-5-6k from the network.
Date: 2013-01-31 04:48:43 UTC The router is on.
Date: 2013-01-31 04:48:25 UTC We are linking the ports between ldn-1-6k and rbx-g1-a9 through new equipment in 100G Infinera (chassis DTN-X).
Date: 2013-01-31 04:35:36 UTC The router is turned off.
We are moving the chassis in the room of the new building TELEHOUSE West.
Date: 2013-01-31 04:34:39 UTC Router isolated.
We will begin disconnecting the fibers.
Date: 2013-01-31 04:33:55 UTC We started isolating the router ldn-1-6k from the network.