OVHcloud Network Status

Current status
Legend
  • Operational
  • Degraded performance
  • Partial Outage
  • Major Outage
  • Under maintenance

[BHS1/BHS4/BHS5/BHS6/BHS7][Infrastructure] - Electrical background work

Scheduled Maintenance Report for Network & Infrastructure

Completed

The scheduled maintenance has been completed.
All the services have been operational since 10:44 UTC.
Posted Sep 25, 2025 - 10:46 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 25, 2025 - 09:50 UTC

Scheduled

As part of our continuous improvement plan, maintenance is scheduled on our electrical infrastructure.

Start time : 25/09/2025 09:50 UTC
End time : 25/09/2025 10:50 UTC
Service impact : Some servers might be temporarily unavailable during 30 minutes.
Service improvement : As part of our continuous improvement policy, we will be doing an electrical maintenance.

From 09:50 UTC to 10:50 UTC, the maintenance may temporarily affect availability of servers

Rooms where you may experience unavailability on BHS4 are: T04A and T04B
Rooms where you may experience unavailability on BHS5 are: T05G, T05D, T05A,T05E, T05B, T05C, T05H, T05F
Rooms where you may experience unavailability on BHS6 are: T06D, T06E, T06B, T06F, T06C, T06G
Rooms where you may experience unavailability on BHS7 are: B710, B709, B707, B702, B703, B716

Our technical teams will be mobilized throughout the maintenance to resolve any impact on your services.

We apologize in advance for any inconvenience caused.
Posted Sep 09, 2025 - 13:58 UTC
This scheduled maintenance affected: Infrastructure || BHS (BHS1, BHS2, BHS3, BHS4, BHS5, BHS6, BHS7).