Following the task # 5807, we will finish tonight our taskworks on telehouse1 to release finally our locations. We will:
- Replace the two links gsw<>th1 and th1<>th2 by a direct link gsw<>th2
- Migrate p19<>th1 to p19<>th2
- Cut the port OTI on th1 (we will reconnect it directly on th2 as soon as FT finalises the migration of its side)
- Disable the router th1-1-6k
- Move all the racks and tools
Work begins tonight from 23:30 CEST(central european summer time).
Update(s):
Date: 2011-10-04 02:39:20 UTC All links are switched on th2.
We took the opportunity to intervene on the route B of Infinera supply(set batteries).
Works are done.
Date: 2011-10-04 00:13:17 UTC The new link gsw <> th2 is set but one of the DWDM lambdas does not remount. It seems to be wired in reverse on th2.
We cut permanently th1-1-6k. Our team is installing the tools that was in th1 and went to th2 in order to fix the problem of the missing lambda and mount the new link p19<>th2.
We start to pass traffic on the new link in order to check the balance at the backbone.
Date: 2011-10-04 00:01:17 UTC We modified the patching in order to create the direct link gsw<>th2.
Date: 2011-10-03 22:09:22 UTC Ditto for th1<>p19.
Date: 2011-10-03 22:06:41 UTC We are re-routing the traffic on the links gsw<>th1 and th1<>th2 in order ti prepare the migration.
Date: 2011-10-03 22:01:49 UTC We started the intervention.