[LIM][Cooling system] - Change the leaking WC hot/cold PVC pipe by copper
Scheduled Maintenance Report for Network & Infrastructure
Completed
The scheduled maintenance has been completed.
Posted Jan 27, 2022 - 07:57 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 27, 2022 - 05:00 UTC
Scheduled
Start time : 27/01/2022 05:00 UTC
End time : 27/01/2022 08:00 UTC
Service impact : Servers in the L105A06 rack may be shut down for material safety reasons during operation
Service improvement : Pipe and water manifold replacement
Posted Jan 18, 2022 - 21:13 UTC
This scheduled maintenance affected: Infrastructure || LIM (LIM1, LIM2, LIM3).