[GRA2][Cooling System] - Racks G219A08/G219A12/G219A15/G219A18 maintenance notification

Scheduled Maintenance Report for Network & Infrastructure

Completed

The scheduled maintenance has been completed.
Posted Mar 18, 2026 - 16:41 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 18, 2026 - 07:45 UTC

Scheduled

As part of our continuous improvement plan, we will be carrying out a maintenance on our cooling infrastructure.

Start time : 18/03/2026 07:45 UTC
End time : 18/03/2026 16:00 UTC

List of concerned racks:
- Rack G219A08
- Rack G219A12
- Rack G219A15
- Rack G219A18

Service impact : During this maintenance, the cooling system's efficiency may be temporarily reduced for some servers, potentially lowering performance. Despite ongoing mitigation efforts, customers could still experience a temporary reboot or shutdown in the worst case.
Service improvement : As part of our continuous improvement policy, we will be doing a maintenance on our cooling infrastructure.

Thank you for your understanding.
Posted Mar 18, 2026 - 07:37 UTC
This scheduled maintenance affected: Infrastructure || GRA (GRA2).